page loader

Our Work:
Leisure and Aquatic

We have a diverse portfolio of successfully completed projects for small to large organisations and government bodies. Our extensive experience spans health, education, manufacturing, infrastructure, defence and retail sectors.

KU-RING-GAI FITNESS AND AQUATIC

Client: Ku-rin-gai Council
Project Type: Development
Project Value: $19 million
Plumbing cost: $1.7 million
Timeframe: Jan 2013- Dec 2014

Ashmor was engaged by Kur-ing-gai Council to deliver on its master plan for a state of the art, community aquatic and recreation centre for its local residents.

The Ashmor team worked collaboratively with the client to manage and overcome ecological complexities at the site, and delivered the project defect free.

Works included sanitary plumbing, trade waste and drainage, black water separation drainage system, extensive stormwater and reuse systems, fire protection and gas supply.

UTS ROWING CLUB

Client: Lipman
Project Type: Redevelopment
Project Value: $6.5 million
Plumbing cost: $450,000
Timeframe: Jan 2013 – Dec 2014

Ashmor was proud to be involved in the redevelopment of Sydney’s iconic UTS Rowing Club.

This Club provides a place for people to access harbour rowing, while enjoying hospitality on the water.

Ashmor worked closely with the builder Lipman and consultants to manage environmental challenges that the site presented during the course of the project.

Leisure and Aquatic 3

WESTPAC PLACE 275 KENT ST SYDNEY

Client: Mirvac
Project Type: Development
Project Value: $18.5 million
Plumbing cost: $850,000
Timeframe: Jan 2018 – May 2020

Top tier builder Mirvac selected Ashmor to relocate stormwater infrastructure to allow for the construction of an end of trip facility. These amenities are valued by staff who choose to walk, run or cycle to work in an effort to stay healthy and reduce pollution. Ashmor’s early involvement in the planning and investigation phases of this project allowed Mirvac to achieve cost savings across this project.

Leisure and Aquatic 4